Construction 4D/5D BIM simulation

Estimated reading: 1 minute 316 views

Playing the 4D/5D simulation in the Schedule Animation view can help to verify the construction schedule visually.

The created 4D/5D simulation can be shared as exported videos, images or through BEXEL Viewer online animation.

To find out more about construction 4D/5D BIM simulation, go to the section Schedule animation.

Based on the created 4D/5D simulation, look-ahead plans for specific construction periods can be generated automatically as the basic input for the on-site team and the progress monitoring process. To learn more about progress monitoring, go to the section Progress monitoring.

Sharing is caring

Construction 4D/5D BIM simulation

Or copy link

IN THIS SECTION: